Published

Chromium Emission System Beats EPA Specs

B.F. Goodrich switched to a CPVC emission control system to meet MACT standards...
#regulation #pollutioncontrol

Share

When B.F. Goodrich's (BFG) Landing Gear Division switched its chromium emissions control system from a wet-pack scrubbing system to dry mist eliminators, it wanted to be certain it met Environmental Protection Agency (EPA) requirements. For safety's sake, it selected a system designer/supplier whose past performance gave clear indication that the Federal EPA MACT standard could be met or exceeded.

The system designer/supplier provided two separate systems for BFG, each serving half of the company's chromium processing lines with the capability of switching from one to the other in the event of an emergency. The company designed a system well below the MACT standard of 0.015 mg/cu meter. The two systems were installed in December, 1995 and January, 1996.

Featured Content

When independent test data was collected and tabulated in July, 1996 both systems were at least 10 times better than the designer's criteria and even lower than the 0.015 mg/cu meter required by the MACT standard.

The BFG facility in Cleveland, Ohio, specializes in finishing large, heavy components weighing as much as two tons. Its primary activity is chromium plating aircraft landing gear and other components for the aerospace industry. It also handles plating of such items as crankshafts for railroad engines. Most of the landing gear components are manufactured at the company's nearby machining facility and shipped to the landing gear facility for final finishing, plating, shot peening and non-destructive testing.

From wet to dry: BFG's solution to satisfy MACT standard. "We had a wet-pack scrubbing system in here before," Thomas M. Wolf, BFG's senior electroplating engineer, pointed out. "When it came time for us to meet the MACT standard, it seemed a good time to make a change."

BFG had learned that multiple-stage, dry mist eliminators were proving most efficient in meeting the MACT standard requirements. In such units, particles are generally trapped by successive media pads or "stages," each with progressively smaller openings to trap increasingly smaller particles by impingement. The pads are periodically washed down to prevent plugging.

"When we decided to change over, we surveyed areas in California since they have some of the most stringent emission laws. We found companies doing work in southern California that could meet the required regulations, and from those firms we requested bids for our project," Mr. Wolf said. "After careful review of five bids and the willingness of the bidders to warranty their installations against MACT standards, we selected KCH Services, Inc." The successful bidder suggested its dry-type, multiple-stage mist eliminators as the solution.

Largest CPVC system built to date. Based on prior corrosion experience, BFG engineers knew they wanted steel hoods for their new system. They specified the steel thickness and the coating desired on both the inside and outside of the hoods. Then they turned the designer's engineers loose to develop the total system design and specifications.

"Other than the hoods, the new system is constructed of CPVC up to the designer's Spectra mist eliminator, at which point it is PVC," Mr. Wolf stated. "To our knowledge, this is the largest CPVC system built to date. It has the largest extruded CPVC duct work (24-inch extruded duct up to 52 inches on the cans), which was hand fabricated from rolled sheet. All phases of construction were monitored by BFG's Corzan Division, specialists in CPVC production and fabrication for corrosion-resistant duct systems."

The new chromium emissions control system goes right from the chromium plating tanks to the roof, approximately one third of the total plating area retrofit, with a price tag of slightly more than $1,000,000. Included in the project was refinishing the floors for corrosion resistance, repainting the tanks and repairing and replacing certain tanks.

There's good reason why the designer's system is divided into two sections, each rated at 40,000 cfm, to service eight chromium plating tanks, two strip tanks and one sulfuric/hydrofluoric tank ranging from 1,000 to 4,000 gal. "Our plating operation runs 24 hours, seven days a week," Mr. Wolf explained. "With the system divided into two sections, we avoid any work interruptions. This is important. If one section goes down, we simply shift our work to the second section, repair the down section and then bring it back on line."

In the system's operation, air is drawn off the top of each plating tank by the 40,000-cfm fans into the vertical, in-line mist eliminator (VME). This first stage removes approximately 99 pct of the 0.05 to 0.1 micron-sized chromium particles. The second stage handles the 0.3 to 0.5 micron or less particles. The air stream is then turned over to a third stage, the coalescing stage, where it takes 0.3 micron or less particles and condenses them back to 0.5 or greater micron particles that are then removed.

Washer system means less chromium, less waste water. "When analyzing our old system," Mr. Wolf said, "we felt it contained a lot of chromium just sitting in it making the system heavier than normal. We requested the designer to design a duct and hood washing system along with the pad and mist eliminator washing systems. All of this is controlled by a simple PLC in cabinet. It's self-monitoring, has its own warning lights and automatically washes itself down on a timed cycle."

According to Mr. Wolf, the system is activated once or twice daily. The pads are washed down every eight hours in the first stage. The last three stages are in cycles. The first two stages in the unit (on the roof) are washed down once every hour. BFG, however, has increased cycle times from the original settings of the designer since its highly efficient wastewater treatment system is capable of handling a greater throughput. As a result, BFG anticipates being able to recycle as much as 90 pct of the treated water. This is an additional benefit that they did not anticipate when installing the designer's system.

"Our previous system was not capable of doing anything like that," Mr. Wolf emphasized. "There was no washing system inside the hoods or ductwork. Everything was scrubbed on the roof. Now, with each tank having its own mist eliminator, we are removing about 90 pct of the chromium, and we can even feed our processed water back into the tank or put it into a holding tank, as we presently do, and draw from it when needed."

In addition to greatly exceeding the MACT standard requirements, Mr. Wolf proudly points out that the new system provides improved shop cleanliness and a better environment for workers. "Our operators could not believe what a change in the atmosphere the new system provided," Mr. Wolf observed.

RELATED CONTENT